Hung Thai Fisheries Logistics Service Port And Lo Voi Port Upgrade And Expansion


HUNG THAI FISHERIES LOGISTICS SERVICE PORT AND LO VOI PORT UPGRADE AND EXPANSION

The Hung Thai Fisheries Logistics Service Port Project and the Lo Voi Port Upgrade and Expansion Project were implemented in Phu My Town, Ba Ria – Vung Tau Province.

VINA E&C participated in the construction of marine structures, rubble-stone prisms, reverse filter layers and auxiliary port equipment.

SCOPE OF WORK

Marine structures

  • Construction of connections between the beams and D500C piles.

  • Supply, installation and removal of pile collars, pile-head bracing and temporary working platforms.

  • Fabrication and installation of formwork and reinforcing steel for the port structures.

  • Supply and placement of concrete for transverse beams, longitudinal beams and pile-cap beams.

  • Construction of deck slabs, load-relief slabs, utility trenches and vehicle curbs.

Rubble-stone prism and reverse filter

  • Supply and construction of the rubble-stone prism.

  • Supply, fabrication and placement of geotextile for the rubble-stone prism.

  • Construction of the reverse filter layer behind the SW600B sheet-pile wall.

Auxiliary berthing equipment

  • Supply and installation of mooring bollards.

  • Installation of marine fenders.

  • Installation of navigation marker posts and signal-light poles.

  • Installation of access ladders and other auxiliary equipment within the contractual scope.

DEMONSTRATED CAPABILITIES

The projects demonstrate VINA E&C’s capabilities in transport and marine construction, particularly port structures, beam-to-pile connections, deck slabs, rubble-stone prisms and berthing equipment.

The integrated execution of reinforced-concrete structures, temporary works, geotechnical works and port equipment required effective construction management, technical coordination and strict control of safety, quality and schedule.

PROJECT INFORMATION

Project 1: Hung Thai Fisheries Logistics Service Port Development Project
Project 2: Lo Voi Port Upgrade and Expansion Project
Package/Scope: Transverse beams, longitudinal beams, pile-cap beams, deck slabs, rubble-stone prism and reverse filter behind the SW600B sheet-pile wall
Location: Phu My Town, Ba Ria – Vung Tau Province
Client: Hung Thai Petroleum Maritime Services Joint Stock Company
Implementation period: 2014–2015
Sector: Transport and Marine Construction


Related projects

Major Repair of Berths No. 5 and No. 6 at Vietsovpetro Port

VINA E&C participated in Major Repair of Berths for Receiving 10,000-DWT Vessels in Vietsovpetro Port, Rach Dua Ward, Ho Chi Minh City, including demolition and salvage of reinforced-concrete berth structures and underwater dredging and more than 11,500 m of d600-c phc piles.

Runway & Taxiway Rehabilitation – Lien Khuong Airport

Runway and taxiway upgrade project at Lien Khuong Airport to meet ICAO 4E standards and improve aviation capacity in the Central Highlands.

The Gia Binh International Airport Construction Investment Project

The Gia Binh International Airport Construction Investment Project is a key aviation infrastructure project in Bac Ninh Province, oriented toward the development of a modern international airport and contributing to regional connectivity in Northern Vietnam. At the project, VINA E&C is updating and carrying out construction works related to the VIP terminal, Air Traffic Control Tower, power house and supporting technical facilities. The current scope includes dismantling load-bearing scaffolding, defect rectification on the ceiling surface of Level 1 – Zone 3.1, construction of foundation tie beams for the VIP terminal and power house, as well as rebar and concrete works for water tanks, fire-fighting water tanks, oil tanks and related structures. The project demonstrates VINA E&C’s capability in organizing construction works for aviation infrastructure, with strong requirements for progress, quality, safety and site coordination.

VINA E&C COMMENCES PACKAGE 25: STRENGTHENING INFRASTRUCTURE AT THUONG PHUOC INTERNATIONAL BORDER GATE

Infrastructure Development for Thuong Phuoc and Moc Ra International Border Gates

UPGRADING ROAD NO. 6, LONG PHUOC WARD

On July 29, 2025, VINA E&C officially commenced the Road No. 6 Upgrade Project in Long Phuoc Ward, Thu Duc City, under Package No. 4 – Construction. The project is commissioned by the Thu Duc City Infrastructure Development Center.

UPGRADE ALLEY 187 LONG PHUOC STREET, LONG PHUOC WARD

Package 4: Construction (including Traffic Safety Assurance costs and contingency fees)

35-ha Petroleum Services Area – Sao Mai – Ben Dinh

VINA E&C participated in Site Filling, Yard Works and Water Supply and Drainage Systems in Vung Tau City, Ba Ria – Vung Tau Province, including embankments for site-filling works and site filling and construction-platform preparation.

Hung Thai ICD General Service Port

Construction work for Phase 2 general port

Package L – Shoreline Protection Works, Long Son Petrochemicals Complex

VINA E&C participated in Package L – Shoreline Protection Works under the Long Son Petrochemicals Complex Project. The scope included port revetments, site formation, internal roads, soft-soil treatment using PVD, flood-protection and drainage systems, a firewater tank and a pump house.