In Tan Duc Commune, Ham Tan District, Binh Thuan Province, the Subdivision No. 3 – Thu Duc Prison project is being implemented with a clear scale and purpose. The Package XL01 covers the complete scope of construction and equipment installation, with the centerpiece being a modern three-story office building designed to meet strict management and operational requirements.
To be implemented in the period from March 26, 2024 to January 7, 2026. With the form of a joint venture, this Grade 2 Civil project not only has infrastructure significance but also contributes to improving management efficiency, creating a synchronous, modern and sustainable working environment.
Item | Information |
---|---|
Project | Sub-camp No. 3 of Thu Duc Prison |
Package | XL01 Construction and installation of all equipment |
Location | Tan Duc Commune, Ham Tan District, Binh Thuan Province |
Investor | Department of Police for management of prisons, compulsory education facilities, and reform schools (C10) |
Contract number | 01/HDXL-BHT-VNEC |
Scale of work | Construction of a 3-storey office building |
Form | Joint venture |
Project level | Civil level 2 |
Status | In progress |
Package 4: Construction
Package 4: Construction (including Traffic Safety Assurance costs and contingency fees)
Construction of site leveling, landfill, drainage system, subdivision 2 (21.5ha)
Package 07: Construction of warehouse and technical infrastructure
Full package of design, appraisal and assessment, construction permit application and construction of COD improvement system
Construction of level 1 leveling level 1 - Division 2 (5.2ha)
Construction of utilities
Xử lý nền đất yếu
Basic construction package 1
Featured projects