VINA E&C is proud to be a subcontractor in the LPG Storage Terminal Project located in Bac Tien Phong, Quang Ninh Province. This is a Grade I industrial project of significant scale, contributing to the expansion and strengthening of Vietnam’s national energy infrastructure.
Within this package, VINA E&C undertakes several critical works:
PROJECT INFORMATION:
| Project | LPG Storage Terminal – Capacity of 176,400 m³ |
| Package | Basic Construction – Package 1 |
| Location | Bac Tien Phong, Quang Ninh Province |
| Client | TTCL Vietnam Co., Ltd |
| Scope of Works | - Earthwork excavation ~30,000 m³ - Construction of foundations for tanks C3 & C4 with 6,000 m³ of concrete and 1,000 tons of steel - Construction of Pipe rack ~1 km |
| Schedule | 23/01/2024 – 15/12/2025 |
| Role | Subcontractor |
| Project Grade | Grade I Industrial Project |
VINA E&C serves as the main contractor for Package No. 07 – Construction of the Warehouse and Technical Infrastructure under the warehouse investment project at Tan Cang Nhon Trach ICD. The project comprises a 6,750 m² warehouse together with surrounding roads, yards, slope protection and integrated technical infrastructure.
VINA E&C participated in Construction of Main Technical Infrastructure – Area A in Phu My, Ba Ria – Vung Tau, including soft soil treatment using the phd method over approximately 91,600 m² and site grading and preparation.
VINA E&C participated in Soft Soil Treatment Package in Phu My Town, Ba Ria – Vung Tau Province, including soft soil treatment using the phd method over approximately 251,000 m².
The Hyosung Advanced Materials Factory project in Ba Ria-Vung Tau Province, undertaken by VINA E&C as the main contractor, focuses on the treatment of a 91,613 m2 area of land using the high-quality PHD method. The project implementation ensures both quality and progress in the work. The goal of the project is to establish a modern and sustainable production infrastructure in the region, contributing to the local economic development and creating numerous employment opportunities.
VINA E&C participated in the construction of utility infrastructure systems for the VARD Plant Expansion Project at Dong Xuyen Industrial Park, Vung Tau City. The scope included drainage systems, MEP trenches and manholes, road-crossing pipes, a 300 m³ underground water tank and a pump station building.
VINA E&C participated in Construction of Infrastructure and Turbine Erection Yard in Vinh Chau Town, Soc Trang Province, including site clearing, cleanup and removal of organic topsoil and site grading and preparation.
VINA E&C participated in Package A2 – Structural Construction Works (Package 1) under the Long Son Petrochemicals Complex Project. The scope included site development, reinforced-concrete tank foundations, pipe-rack foundations, structural steel works, underground piping and drainage systems.
VINA E&C participated in the construction and installation of Bulk Cargo Warehouse No. 1 at Thi Vai General Port, Ba Ria – Vung Tau Province. The 6,424 m² facility was developed to support bulk-cargo storage and port operations.
VINA E&C participated in the construction of technical infrastructure, warehousing facilities and the Hung Thai Maritime Service Port in Phu My Town, Ba Ria – Vung Tau Province. The scope included two warehouses with a combined area of 39,482 m², internal roads, a weighbridge, piling works, dredging and a cargo berth.