CARBON FIBER AND MATERIALS FACTORY PROJECT


The Hyosung Advanced Materials Factory project in Tan Thanh District, Ba Ria-Vung Tau Province, is an initiative undertaken by VINA E&C as the main contractor. The project focuses on the treatment of a 91,613 m2 area of land using the high-quality PHD method. With the groundbreaking ceremony taking place on September 5, 2023, the project is actively progressing.

VINA E&C not only acts as the project executor but also ensures both the quality and timely completion of the work. The project marks a significant step in the collaboration between VINA E&C and Hyosung Advanced Materials, promising positive contributions to the local economic development and the creation of numerous job opportunities. Through the synergy of VINA E&C and modern technology, the project aims to establish a modern and sustainable production infrastructure in the region.

General Information:

PROJECT: Carbon Fiber Production plant
CONTRACT PACKAGE: Ground Treatment
PROJECT LOCATION: B7 Area, N2 Road, Phú Mỹ II Industrial Zone, Ba Ria -Vung Tau Province
INVESTOR / MAIN CONTRACTOR: Hyosung Vina Core Materials Co.,LTD
JOB DESCRIPTION: Strengthening Weak Ground through PVD, PHD, and Conventional Load Bearing Techniques
DURATION: 05/09/2023 - ….
ROLE: Main contractor
STATUS: In progress

Related projects

Tan Cang Nhon Trach ICD Warehouse

VINA E&C serves as the main contractor for Package No. 07 – Construction of the Warehouse and Technical Infrastructure under the warehouse investment project at Tan Cang Nhon Trach ICD. The project comprises a 6,750 m² warehouse together with surrounding roads, yards, slope protection and integrated technical infrastructure.

CARBON FIBER AND MATERIAL FACTORY - CONSTRUCTION UTILITIES

VINA E&C participated in Construction of Main Technical Infrastructure – Area A in Phu My, Ba Ria – Vung Tau, including soft soil treatment using the phd method over approximately 91,600 m² and site grading and preparation.

Bio-BDO Biological Products Factory

VINA E&C participated in Soft Soil Treatment Package in Phu My Town, Ba Ria – Vung Tau Province, including soft soil treatment using the phd method over approximately 251,000 m².

VARD PLANT EXPANSION – UTILITY INFRASTRUCTURE SYSTEMS

VINA E&C participated in the construction of utility infrastructure systems for the VARD Plant Expansion Project at Dong Xuyen Industrial Park, Vung Tau City. The scope included drainage systems, MEP trenches and manholes, road-crossing pipes, a 300 m³ underground water tank and a pump station building.

Lac Hoa II Wind Power Plant

VINA E&C participated in Construction of Infrastructure and Turbine Erection Yard in Vinh Chau Town, Soc Trang Province, including site clearing, cleanup and removal of organic topsoil and site grading and preparation.

Package A2 – Long Son Petrochemicals Complex

VINA E&C participated in Package A2 – Structural Construction Works (Package 1) under the Long Son Petrochemicals Complex Project. The scope included site development, reinforced-concrete tank foundations, pipe-rack foundations, structural steel works, underground piping and drainage systems.

Bulk Cargo Warehouse No. 1 – Thi Vai General Port

VINA E&C participated in the construction and installation of Bulk Cargo Warehouse No. 1 at Thi Vai General Port, Ba Ria – Vung Tau Province. The 6,424 m² facility was developed to support bulk-cargo storage and port operations.

Hung Thai Technical Infrastructure, Warehousing And Maritime Service Port

VINA E&C participated in the construction of technical infrastructure, warehousing facilities and the Hung Thai Maritime Service Port in Phu My Town, Ba Ria – Vung Tau Province. The scope included two warehouses with a combined area of 39,482 m², internal roads, a weighbridge, piling works, dredging and a cargo berth.