The project to upgrade and expand Lo Voi port is invested by Hung Thai Petroleum Maritime Services Joint Stock Company, with the goal of increasing exploitation capacity, meeting the increasing demand for maritime transport in the key economic region of the South.
VINA E&C was selected as the main contractor, directly undertaking important construction items:
With a total contract value of more than 140 billion VND, the project demonstrates the investor's trust in the reputation and construction capacity of VINA E&C.
General information:
| PROJECT: | INVESTMENT PROJECT TO UPGRADE AND EXPAND LO VOI PORT |
| CONTRACT PACKAGE: | Horizontal and vertical girder system, cap girder, bridge deck & Rock prism, reverse filter layer behind SW600B sheet pile wall |
| PROJECT LOCATION: | Phu My Town, Ba Ria - Vung Tau Province. |
| INVESTOR / MAIN CONTRACTOR: | Hung Thai Petroleum Maritime Services Joint Stock Company |
| JOB DESCRIPTION: | - Construction of the connection system between beams and D500C piles. - Supply, install, remove pile clamps, pile head clamps and construction floor system. - Supply and construction of boulder foundations. - Supply, sew, fold edges, load geotextiles for boulder foundations. - Supply and install anchor flanges, bumpers, signal columns, signal light posts, and ladders. |
| DURATION: | 2014 - 2015 |
| ROLE: | Main contractor |
| STATUS: | In progress |
Runway and taxiway upgrade project at Lien Khuong Airport to meet ICAO 4E standards and improve aviation capacity in the Central Highlands.
The Gia Binh International Airport Construction Investment Project is a key aviation infrastructure project in Bac Ninh Province, oriented toward the development of a modern international airport and contributing to regional connectivity in Northern Vietnam. At the project, VINA E&C is updating and carrying out construction works related to the VIP terminal, Air Traffic Control Tower, power house and supporting technical facilities. The current scope includes dismantling load-bearing scaffolding, defect rectification on the ceiling surface of Level 1 – Zone 3.1, construction of foundation tie beams for the VIP terminal and power house, as well as rebar and concrete works for water tanks, fire-fighting water tanks, oil tanks and related structures. The project demonstrates VINA E&C’s capability in organizing construction works for aviation infrastructure, with strong requirements for progress, quality, safety and site coordination.
Construction work for Phase 2 general port
Featured projects