The Long Bình Metrocity GS project is one of the key technical infrastructure developments in Thu Duc City, Ho Chi Minh City, in which VINA E&C proudly serves as the Main Contractor. This stage focuses on the construction of the primary infrastructure system for Zone A, covering transportation networks, drainage, water supply, power distribution, lighting, and landscaping. The project represents a vital foundation for shaping a modern and sustainable urban area, while also contributing to the long-term vision of building a well-planned and environmentally friendly city.
Project information:
Project | Long Bình Metrocity GS – Zone A |
Package | Construction of main technical infrastructure for Zone A |
Location | Long Bình Ward, Thu Duc City, Ho Chi Minh City |
Investor | Vietnam GS Enterprise Co., Ltd. |
Scope of Work | - Construction of 2.4 km asphalt concrete road - Installation of stormwater and wastewater drainage systems - Water supply, electricity distribution, and communication networks - Street lighting and landscaping works - Synchronization with transportation facilities |
Timeline | March 01, 2023 – February 01, 2025 |
Role | Main Contractor |
Status | Ongoing |
Construction of working houses and auxiliary items ( including: construction, air conditioning system, lightning protection system )
Construction of bridge 1 and 2
Internal Technical Infrastructure of Phase 1-1
Supply of sand sediment, pump up the ground, leveling & dyke construction around the park