TRAN CHAU FISHING PORT – PACKAGE NO. 5: JETTY CONSTRUCTION


TRAN CHAU FISHING PORT – PACKAGE NO. 5: JETTY CONSTRUCTION

The Tran Chau Fishing Port Development Project was implemented on Cat Ba Island, Cat Hai District, Hai Phong City.

As part of the project, VINA E&C participated in Package No. 5 – Jetty Construction.

The package covered jetty construction, dredging of the port-water areas, installation of navigation buoys and construction of facilities supporting fish reception, sorting and preliminary processing activities.

SCOPE OF WORK

Jetty construction

  • Construction of the jetty structures.

  • Placement of approximately 1,100 m³ of concrete.

  • Construction of auxiliary works within the jetty scope.

Dredging works

  • Dredging of the navigation channel.

  • Dredging of the turning basin.

  • Dredging of the storm-shelter anchorage area.

  • Associated works for the navigation buoy system.

  • Total dredging volume of approximately 650,500 m³.

Fishing-port operational facilities

  • Construction of the fish reception building.

  • Construction of the fish sorting and preliminary processing area.

  • Construction of the firefighting water-supply system.

  • Total facility area of approximately 1,500 m².

KEY PROJECT QUANTITIES

  • Jetty concrete: Approximately 1,100 m³.

  • Dredging volume: Approximately 650,500 m³.

  • Fish reception, sorting and preliminary processing facilities: Approximately 1,500 m².

DEMONSTRATED CAPABILITIES

The project demonstrates VINA E&C’s capabilities in transport and marine construction, combining jetty structures, dredging and fishing-port operational facilities.

The simultaneous execution of onshore and marine works required multidisciplinary construction management, equipment coordination and strict control of safety, quality, environmental requirements and schedule.

PROJECT INFORMATION

Project: Tran Chau Fishing Port Development Project on Cat Ba Island
Package: Package No. 5 – Jetty Construction
Location: Cat Ba Island, Cat Hai District, Hai Phong City
Client: Hai Phong Agriculture and Rural Development Project Management Board
Implementation period: 26 April 2018 – 22 August 2019
Sector: Transport and Marine Construction
Principal works: Jetty, dredging, navigation buoys, fish reception and processing facilities



Related projects

Major Repair of Berths No. 5 and No. 6 at Vietsovpetro Port

VINA E&C participated in Major Repair of Berths for Receiving 10,000-DWT Vessels in Vietsovpetro Port, Rach Dua Ward, Ho Chi Minh City, including demolition and salvage of reinforced-concrete berth structures and underwater dredging and more than 11,500 m of d600-c phc piles.

Runway & Taxiway Rehabilitation – Lien Khuong Airport

Runway and taxiway upgrade project at Lien Khuong Airport to meet ICAO 4E standards and improve aviation capacity in the Central Highlands.

The Gia Binh International Airport Construction Investment Project

The Gia Binh International Airport Construction Investment Project is a key aviation infrastructure project in Bac Ninh Province, oriented toward the development of a modern international airport and contributing to regional connectivity in Northern Vietnam. At the project, VINA E&C is updating and carrying out construction works related to the VIP terminal, Air Traffic Control Tower, power house and supporting technical facilities. The current scope includes dismantling load-bearing scaffolding, defect rectification on the ceiling surface of Level 1 – Zone 3.1, construction of foundation tie beams for the VIP terminal and power house, as well as rebar and concrete works for water tanks, fire-fighting water tanks, oil tanks and related structures. The project demonstrates VINA E&C’s capability in organizing construction works for aviation infrastructure, with strong requirements for progress, quality, safety and site coordination.

VINA E&C COMMENCES PACKAGE 25: STRENGTHENING INFRASTRUCTURE AT THUONG PHUOC INTERNATIONAL BORDER GATE

Infrastructure Development for Thuong Phuoc and Moc Ra International Border Gates

UPGRADING ROAD NO. 6, LONG PHUOC WARD

On July 29, 2025, VINA E&C officially commenced the Road No. 6 Upgrade Project in Long Phuoc Ward, Thu Duc City, under Package No. 4 – Construction. The project is commissioned by the Thu Duc City Infrastructure Development Center.

UPGRADE ALLEY 187 LONG PHUOC STREET, LONG PHUOC WARD

Package 4: Construction (including Traffic Safety Assurance costs and contingency fees)

35-ha Petroleum Services Area – Sao Mai – Ben Dinh

VINA E&C participated in Site Filling, Yard Works and Water Supply and Drainage Systems in Vung Tau City, Ba Ria – Vung Tau Province, including embankments for site-filling works and site filling and construction-platform preparation.

Hung Thai ICD General Service Port

Construction work for Phase 2 general port

Package L – Shoreline Protection Works, Long Son Petrochemicals Complex

VINA E&C participated in Package L – Shoreline Protection Works under the Long Son Petrochemicals Complex Project. The scope included port revetments, site formation, internal roads, soft-soil treatment using PVD, flood-protection and drainage systems, a firewater tank and a pump house.