On October 27, 2026, VINA E&C continued to mobilize manpower and equipment to advance construction activities under Packages 24 and 25 of the Thuong Phuoc – Moc Ra International Border Gate Infrastructure Project in Dong Thap Province, with a focus on safety, quality, and project progress.
Under Package 24, sand filling works had reached approximately 154,000 out of 170,000 cubic meters, exceeding 90% of the planned volume as of October 25, 2026. Bridge construction was progressing, with concrete deck casting completed for two of seven spans. Subsequent construction activities and preparations for roadbed and pavement works were also underway.
Under Package 25, multiple construction operations continued simultaneously, including earthworks, roadbed compaction, sand filling, embankment construction, geotextile reinforcement, and ground improvement.
Bridge works included reinforcing steel installation for the T4–T5 deck span, installation of concrete cover slabs, and related structural activities. Preparations for technical infrastructure and finishing components were also in progress.
The project continues to face challenges related to construction material availability, particularly crushed stone aggregates required for road construction.
VINA E&C is coordinating with relevant departments to secure additional material supplies, optimize resource allocation, and prepare supporting components to maintain construction continuity.
On October 27, Mr. Vu Van Liem, General Director of VINA E&C, visited the construction site to review actual progress and discuss practical solutions with the project management team.
Through proactive coordination and resource mobilization, VINA E&C remains committed to advancing construction activities while maintaining safety and quality standards.
Upon completion, the Thuong Phuoc – Moc Ra International Border Gate Infrastructure Project is expected to strengthen regional transport connectivity, facilitate cross-border trade, and contribute to the socio-economic development of Dong Thap Province.
VINA E&C – Sustainable links - Building the future.






On October 20, 2026, VINA E&C officially broke ground on the 2.65-hectare CBU Yard Expansion Project at Saigon Premier Container Terminal (SPCT), Hiep Phuoc, Ho Chi Minh City, further strengthening its presence in port infrastructure construction through the Design & Build (D&B) delivery model.
VINA E&C has been awarded a construction contract for the Stavian Aluminium Packaging Foil Rolling Plant at Quan Do Industrial Cluster, Doan Dao Commune, Hung Yen Province. The project adds to the Company’s industrial construction portfolio.
Under the theme “Healthy Today – Confident Steps Tomorrow”, VINA E&C is rolling out its 2026 employee health check-up programme across its offices and project sites. Scheduled for completion before 25 October 2026, the programme reflects the Company’s commitment to employee health and well-being.