VINA E&C takes on the role of main contractor in the Investment and Construction Project of the 35ha Oil & Gas Service Zone – Subzone 1, Phase 2, developed by Sao Mai – Ben Dinh Oil & Gas Investment JSC. This is a key project in the oil & gas sector in Ba Ria – Vung Tau, aiming to establish a modern oil & gas service complex to support exploration, processing, and logistics activities.
The primary scope of work includes building sand embankments and site leveling with 300,000 m³ of sand over an area of 5.2 hectares. Given the large-scale foundation requirements, VINA E&C is applying advanced technical solutions to ensure construction progress, safety, and quality, providing a solid foundation for future development phases.
Category | Details |
---|---|
Project Name | Investment in the Construction of the 35ha Oil & Gas Service Zone – Subzone 1 (Phase 2 – 5.2ha) |
Package | Land reclamation and site leveling for Subzone 1 – Phase 2 |
Location | Vung Tau City, Ba Ria – Vung Tau Province |
Developer | Sao Mai – Ben Dinh Oil & Gas Investment JSC |
Scope of Work | Sand embankment construction and site leveling with 300,000 m³ of sand over 5.2ha |
Execution Time | 30/08/2024 – 09/01/2025 |
Role | Main Contractor |
Status | Ongoing |
Package 4: Construction
Package 4: Construction (including Traffic Safety Assurance costs and contingency fees)
Construction of site leveling, landfill, drainage system, subdivision 2 (21.5ha)
Package 07: Construction of warehouse and technical infrastructure
Full package of design, appraisal and assessment, construction permit application and construction of COD improvement system
Construction of utilities
Xử lý nền đất yếu
Package XL01: Construction and installation of all equipment
Basic construction package 1
Featured projects